From JIM KELLEY, Paa-Ko Board of Directors
Western Petroleum Pipeline Easement Update
We have spoken with Marathon Petroleum’s spokesperson at SelectRow about the new activity along the Western Refinery Pipeline easement through PaaKo Communities. Although the new pipe was installed and tested this past spring, it had not been tied into the existing operating pipe. They are preparing for that connection now, and work will start around the 21st and continue through the end of the month if things go well.
There were other issues covered on the conference call:
** The reseeding of the disturbed soil did not take root and will be redone.
** The right-of-way fencing around the Twin Arrow gate area will be repaired.
** The damaged culvert issue will be examined immediately, and a solution will be proposed.
** Remediation grading will be performed to address residential drainage problems.